  • C&M Engineering S.A.
    Aliveri in Evia island Greece The project consists of the following main facilities and components 58 5 km of 20 inch diameter high pressure gas pipeline Three Line Valve Stations Two Terminal Scraper Stations Hot Tapping at existing Stefani LVS for the connection of the new pipeline system with the existing main pipeline being in operation Tie in activities of the onshore and the offshore pipeline systems nearby the shore

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/10_Aliveri/10_Aliveri_b.html (2016-02-13)
    Open archived version from archive


  • C&M Engineering S.A.
    Aliveri in Evia island Greece The project consists of the following main facilities and components 58 5 km of 20 inch diameter high pressure gas pipeline Three Line Valve Stations Two Terminal Scraper Stations Hot Tapping at existing Stefani LVS for the connection of the new pipeline system with the existing main pipeline being in operation Tie in activities of the onshore and the offshore pipeline systems nearby the shore

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/10_Aliveri/10_Aliveri_c.html (2016-02-13)
    Open archived version from archive

  • C&M Engineering S.A.
    Aliveri in Evia island Greece The project consists of the following main facilities and components 58 5 km of 20 inch diameter high pressure gas pipeline Three Line Valve Stations Two Terminal Scraper Stations Hot Tapping at existing Stefani LVS for the connection of the new pipeline system with the existing main pipeline being in operation Tie in activities of the onshore and the offshore pipeline systems nearby the shore

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/10_Aliveri/10_Aliveri_d.html (2016-02-13)
    Open archived version from archive

  • C&M Engineering S.A.
    Aliveri in Evia island Greece The project consists of the following main facilities and components 58 5 km of 20 inch diameter high pressure gas pipeline Three Line Valve Stations Two Terminal Scraper Stations Hot Tapping at existing Stefani LVS for the connection of the new pipeline system with the existing main pipeline being in operation Tie in activities of the onshore and the offshore pipeline systems nearby the shore

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/10_Aliveri/10_Aliveri_e.html (2016-02-13)
    Open archived version from archive

  • C&M Engineering S.A.
    Transmission System NGTS of DESFA at Vaya with the new 400 MW Combined Cycle Power Plant of THISVI PGP placed at the Industrial Area of THISVI The project consists of the following main facilities and components 26 3 km of 20 inch diameter high pressure gas pipeline One Line Valve Station Two Terminal Scraper Stations SCADA and Telecommunication System integrated with the existing NGTS control system Provided Services Detailed Engineering

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/11_Thisvi/11_Thisvi_b.html (2016-02-13)
    Open archived version from archive

  • C&M Engineering S.A.
    Transmission System NGTS of DESFA at Vaya with the new 400 MW Combined Cycle Power Plant of THISVI PGP placed at the Industrial Area of THISVI The project consists of the following main facilities and components 26 3 km of 20 inch diameter high pressure gas pipeline One Line Valve Station Two Terminal Scraper Stations SCADA and Telecommunication System integrated with the existing NGTS control system Provided Services Detailed Engineering

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/11_Thisvi/11_Thisvi_c.html (2016-02-13)
    Open archived version from archive

  • C&M Engineering S.A.
    API 5L X65 design pressure 70 barg cathodic protection system 2 scraper stations High Pressure Gas Pipeline to West Thessalia Ambelia Karditsa Trikala NPS 10 72 Km material API 5L X65 design pressure 70 barg cathodic protection system 3 line valve stations along the route and 2 scraper stations relocation of two M R stations and RCC system High Pressure Pipeline to Aliveri Evia Island NPS 20 58 Km onshore and 14 Km offshore marine crossing material API 5L X65 design pressure 80 barg cathodic protection system 3 line valve stations along the route and 2 scraper stations Metering Station at ADG Installation of Metering Station to feed the power plant in the industry Aluminium of Greece A D G at Aspra Spitia Viotia with max capacity 100 000 Nm3 h and installation of RCC system Metering Station at PPC Aliveri Evia Island Installation of metering station to feed the PPC power plant at Aliveri with max capacity 160 000 Nm3 h and installation of RCC system Nea Messimvria Compressor Station Installation of two gas turbine driven compressors with absorbed power 7 5 MW each operating flow range from 257 400 to 445 800 Nm3 h and pressure ratio 1

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/18_HPNG/18_HPNG_b.html (2016-02-13)
    Open archived version from archive

  • C&M Engineering S.A.
    API 5L X65 design pressure 70 barg cathodic protection system 2 scraper stations High Pressure Gas Pipeline to West Thessalia Ambelia Karditsa Trikala NPS 10 72 Km material API 5L X65 design pressure 70 barg cathodic protection system 3 line valve stations along the route and 2 scraper stations relocation of two M R stations and RCC system High Pressure Pipeline to Aliveri Evia Island NPS 20 58 Km onshore and 14 Km offshore marine crossing material API 5L X65 design pressure 80 barg cathodic protection system 3 line valve stations along the route and 2 scraper stations Metering Station at ADG Installation of Metering Station to feed the power plant in the industry Aluminium of Greece A D G at Aspra Spitia Viotia with max capacity 100 000 Nm3 h and installation of RCC system Metering Station at PPC Aliveri Evia Island Installation of metering station to feed the PPC power plant at Aliveri with max capacity 160 000 Nm3 h and installation of RCC system Nea Messimvria Compressor Station Installation of two gas turbine driven compressors with absorbed power 7 5 MW each operating flow range from 257 400 to 445 800 Nm3 h and pressure ratio 1

    Original URL path: http://cmengineering.gr/Projects%20Html/Energy/18_HPNG/18_HPNG_c.html (2016-02-13)
    Open archived version from archive



  •